BROWNSVILLE, Texas (AP) — On a one-acre site alongside a string of shrimp boats docked on the Brownsville ship channel stands a $2.2 million assembly of pipes, sheds, and humming machinery — Texas’ entrance into global efforts to make seawater suitable to drink.

Opening a small spigot at the end of a fat pipe, plant operator Joel del Rio fills a plastic glass with what he says will taste “like regular bottled water.”

“Seawater,” he said. “It’s never gonna run out.”

The plant is a pilot project for the state’s $150 million, full-scale seawater desalination plant slated for construction in 2010.

Desalting seawater is expensive, mostly because of the energy required. Cost estimates run at $650 per acre-foot (326,000 gallons), as opposed to $200 for purifying the same amount of fresh water.

However, it is a growing field around the world as governments and private investors ante up where drinkable-water needs are crucial.

About two-thirds of the world’s desalinated water is produced in Saudi Arabia, Kuwait and North Africa. Perth, Australia, is looking to meet a third of its fresh water demand by removing salt from seawater.

In March, Israel showed off its plant at the Mediterranean port of Ashkelon that can process 87 million gallons of water a day. Singapore opened a seawater desalination plant in 2005 with hopes that it will meet at least 10 percent of its water needs. Two months ago, General Electric Co. announced a $220 million contract to build a plant in South Africa.

Global output is still relatively minute — less than 0.1 percent of all drinking water. But according to a report by Global Water Intelligence, the worldwide desalination industry is expected to grow 140 percent over the next decade, with $25 billion in capital investment by 2010, or $56 billion by 2015.

While the U.S. has hundreds of plants to purify brackish groundwater, desalination of saltier seawater is just getting started. In Florida, a $158 million seawater desalination plant in the Tampa Bay area opened in March after years of delays.

California hopes to get about a half-million acre-feet of water a year from desalination, said Fawzi Karajeh, chief of water recycling and desalination for the state Department of Water Resources.

That may seem a tiny portion of the state’s yearly requirement of 70 million acre-feet, “but every drop counts,” Mr. Karajeh said. An acre-foot will supply two homes for one year.

Texas Gov. Rick Perry began pushing for Gulf of Mexico desalination in 2002, after a state water plan determined that hundreds of communities face water shortages in the next 50 years.

The Brownsville venture got fast-tracked during a period of alarming drought and rapid population growth. From 1990 to 2000, the Brownsville area grew 43 percent to 372,000 people, and the population is expected to approach 500,000 by 2020.

Every drop of the Rio Grande, the river shared by Texas and Mexico, is already accounted for. A plant that purifies brackish groundwater provides enough water to meet about one-fourth of Brownsville’s peak demand, but groundwater may not last through a long-term drought.

Desalination is “part of the tools in the toolbox” of 4,500 water management strategies in the state’s water plan, Texas Water Development Board spokeswoman Carla Daws said.

“We should never become complacent because of the history of our state having repeated droughts,” she said.

Water pumped into the plant goes to three separate pretreatment units, designed by three separate companies hoping to win a contract for the full-scale plant. Chemicals and filtration remove bacteria, sediment and other impurities. The cleaned but still salty water then goes to the reverse-osmosis equipment, where it is pumped at high pressure through a process that separates dissolved salt molecules from the water, producing one stream of purified water and a second of concentrated brine that is returned to the sea.